Renovation Updates

Renovation Updates

  1. Photo of Meyer LibraryRe-Carpeting the southwest section of the Second Level (the “Wedge”): Earlier this week PD&C (the office of Planning, Design, and Construction) informed the Libraries that the new carpeting would arrive sometime during the week of August 14th, and will take approximately four days to install. Once we receive confirmation that the new carpeting has shipped, we may be able to have the old carpeting removed and the floor surface prepped before the new carpet actually arrives. The installers have agreed to work through the weekend prior to the start of fall semester classes, if necessary. Furniture will be ready to be deployed as soon as the new carpeting is installed. Classes begin on Monday, August 21st.
  2. The assembly and deployment of furnishings into the RIS Commons is scheduled to begin on Friday, August 4th. This job should be completed by Tuesday, August 8th. The ordering and installation of a new service desk is a separate project, with no specified completion date yet.